These five crates represent one of the air handler units for Howe
Hall. There will be eight such units total.
(June 3)
|

Here's the top floor where some of the air handler units will
be installed.
|

Some of the impressive duct work that has been installed in the
building.
|

More of the duct work, this in the Southwest portion of Howe Hall. |

In the basement, some of the water pumps have been set in place. |

Everything but the kitchen sink--here are toilet hangers that
will be put in the walls of the restrooms. |
|

Much of the ceiling duct work has been put in place on the first
floor of the South side.
|
|