
Some of the most noticeable progress on the building has been
the placement of the roof beams over the high-bay area. Here
two of the beams arrive at the site pulled by a semi truck.
(June 19)
|

This is the first beam being lifted in place. Notice the attached
safety line used by the steel workers.
|

As the beam nears it's final location, steel workers on either
side guide the beam in place.
|

A close-up of the steel workers attaching the beam to the column. |

This is one of the later beams being hoisted up toward the West
end of the building.
(June 24) |

It's a tight fit and required a skilled crane operator to lift
beam without incident. |

Steel workers guiding the beam.
|

Some minor coaxing of the beam and it is bolted in place.
|

Once the beams were placed, workers began to locate the trusses
that will support the roof.
|

One of the steel workers sliding a truss into place.
|

Masonry work continues on the auditorium wall.
|

A good portion of the South wall has the brickwork in place.
|